|
MIDSHORE I:
New
Cell Construction is underway.
George and Lynch,
Inc. General
Contractors from Delaware, started construction of Cell #
4, the final element in the MIDSHORE I design, in
September 2006 and are expected to finish before May 1st
of this year. The new cell is designed to hold
approximately 800,000 tons of waste.
This will provide adequate capacity for the four
Midshore Counties through the schedule closure of MIDSHORE
I at the end of CY 2010.

Midshore
I Cell #4 Construction
MIDSHORE II:
Geosyntec
Consultants, Columbia, MD area office, has been selected
as the lead design firm for MIDSHORE II, which is to be
built near the Town of Ridgely. This new state of the art
facility is to be opened in Caroline County in 2011.
|