Location:

West of Fort George G. Meade in western Anne Arundel County, Md.

Constructed:

Built in 1988, MES began construction of plant in 1976 and still operates today

Design flow:

2 million gallons per day

Actual flow:

1.5 million gallons per day

Process:

Advanced wastewater treatment plant.  Flow equalization, primary sedimentation, phosphorus control, nitrification, denitrification, filtration and effluent disinfection utilizing U.V. disinfection.

 

 